- Salado Independent School District
- Homepage
Return to Headlines
Superintendent's Corner
The construction continues on our new high school and stadium that are scheduled to be completed in August 2026.
These are the activities our general contractor and subcontractors worked on last week:
- Placed interior grade beams at Area C
- Area A underground plumbing complete
- Area A electrical feeder complete
- Began fire loop at high school site
- High school sanitary sewer complete
- Completed bore under middle school driveway
These are the activities our general contractor and subcontractors are working on this week:
- Place Area C exterior grade beams
- Underground electrical Area B
- Underground plumbing Area B
- Continue buyout and submittal review
- Lay hydromulch on running hill
- Place Area A elevator pit walls
If you have any questions regarding the construction of these new facilities you are welcome to contact me at michael.novotny@saladoisd.org or 254-947-6905.